Installation method of vacuum atmosphere furnace

の設置方法 真空雰囲気炉

Vacuum atmosphere furnaces are now used in many industrial manufacturing in the heating process. For the atmosphere furnace, we should first understand the structure of the atmosphere furnace before operating, in order to have a better operation of the atmosphere furnace, and to deal with various conditions in time during operation. .

The structure of the atmosphere furnace is mainly composed of a furnace frame, a furnace shell, a furnace lining, a furnace door device, an electric heating element and an auxiliary device. The function of the furnace frame is to bear the load of the furnace lining and the workpiece, and usually there are section steel welded into a frame, and the steel plate is covered. The function of the furnace shell of the vacuum atmosphere furnace is to protect the furnace lining, strengthen the structure of the electric furnace and maintain the airtightness of the electric furnace. The steel plate is usually welded on the steel frame. The reasonable design of the furnace frame and the furnace shell has sufficient strength. Let’s take a look at the installation method:

1.真空雰囲気炉は特別な設置は必要なく、平らな地面または作業台に置くだけで済みます。 コントローラは振動を避け、過熱を防ぐために電気炉に近すぎないようにし、電子部品が正常に動作しないようにする必要があります。

2. Before installing the electric furnace, check whether it is damaged or incomplete due to transportation or other reasons. If it is complete, remove the dirt from the parts first, repair the defects found, and then install it.

3.熱電対をカップル穴に挿入し、熱損失を防ぐために、カップル穴と熱電対の間の隙間をアスベストロープで埋めます。

4.真空雰囲気炉の電気発熱体が壊れたり、ひびが入ったり、ひどく曲がったり、レンガから落ちたりしていないか確認してください。

5.電源コード、電気炉コード、補償線の接続は、コントローラマニュアルの配線図を参照してください。

6. After the wire is connected, please follow the procedure below to bake the new vacuum atmosphere furnace before using it for the first time.