site logo

Бойлерийн галд тэсвэртэй тоосго хэрхэн яаж барих вэ?

-ийн галд тэсвэртэй тоосго хэрхэн яаж барих вэ бойлер?

1. The construction steps are carried out in accordance with the principle of from bottom to top and from inside to outside. The lower part of the upper drum and the convection tube bundle interval flame plate are poured from top to bottom.

2. The furnace wall has high air-tightness requirements, and the fullness of ash joints: red bricks are not less than 85%; refractory bricks are not less than 90%. The squeezing method is used for red brick masonry, and the scraping method is used for refractory brick masonry.

3. Masonry of furnace bottom:

(1) Before the furnace bottom is laid, the foundation should be leveled, and the surrounding straight walls in contact with the furnace bottom should be built first, and the height should be approximately higher than the surface of the furnace bottom. Then mark the horizontal line of the furnace bottom (in the case of multi-layer masonry, together with the number of layers) on the straight wall before the furnace bottom can be built.

(2) When the furnace bottom is composed of multiple layers of bricks, the masonry should be carried out layer by layer, with the upper and lower layers and the same layer of bricks staggered, and the long sides of the most surface layer bricks are perpendicular to the flow direction of slag or gas.

(3) In high-temperature areas and furnace bottoms that often need to be overhauled, an expansion gap should be left at the contact between the furnace bottom and the straight wall, and asbestos rope or pad asbestos board should be embedded in the gap.

4. Masonry of ash bucket (including inclined wall):

(1) Үнс шанага барихын өмнө эхлээд зургийн дагуу хэвтээ тэнхлэгийн шугамыг олж, хэвтээ төвийн шугамыг ашиглан үнсний сав бүрийн уртааш тэнхлэгийн шугам, зузаан шаарын урд болон хойд шулуун хананы гадна ирмэгийг олно. хувин, дараа нь өндрийг хоёр төгсгөлд нь суурьлуулна. Үнсний савны ёроолд босоо төвийн шугамыг дээшлүүлж, үнсний савны ёроолд хэмжээг тохируулна. Босоо туслах шугамыг гаргасны дараа үйлдвэрлэсэн гурвалжингийн загварыг (зураг дээрх налуу хананы налуугийн дагуу хийсэн) ашиглаж, налуу хананы хажуугийн шугамыг суурийн суурийн хоёр төгсгөлд зурна. Гадаргуу. Галд тэсвэртэй бетоны ижил материалыг ашиглан налуу хананы ёроолд гурвалжин хэлбэрийн ухралт хийж (1-р зурагт үзүүлсний дагуу) шулуун ханыг тэгшлэнэ. Босоо, хэвтээ ба налуу хананы уулзвар дахь гурвалжин хэлбэрийн ухралтыг мөн ижил материалын галд тэсвэртэй бетоноор цутгаж байх ёстой. Өрлөгийн налуу ханыг үргэлжлүүлнэ.

(2) When building the ash bucket, first build the horizontal and then the vertical; when the inclined wall and the straight wall are formed, build the straight wall first and then the inclined wall.

(3) When there is foundation support on the back of the inclined wall, the mortar on the contact surface between the bricks and the foundation should be full; Once cinder, cinder must be compacted.

5. Шулуун хананы өрлөг:

(1) The straight walls around the boiler are composed of refractory bricks, thermal insulation bricks (or thermal insulation layer), and red bricks. The order of masonry construction is to build refractory bricks first, then thermal insulation bricks (or paste insulation boards or felt), and finally red bricks. For example, when the hot joint between the refractory brick and the red brick is filled, the filler should be filled every 3 to 4 layers of the red brick, and the filling should be dense.

(2) Шулуун ханыг барихдаа зуухны хананы буланд байрлуулсан байх ёстой. Шулуун хэсгийн хоёр үзүүрийг 2-3 давхар толгойтой хашаатай байх ёстой бөгөөд хэвтээ шугамыг барьж байх ёстой. Зуурмагийн үеийг барьж, өргөтгөлийн үеийг хэвээр үлдээж, босоо өргөтгөлийн асбест олсыг өлгөж, өрлөгийг үргэлжлүүлэхийн өмнө ган хүрээний фасад дээр асбест хавтанг наана.

(3) The masonry method of straight wall masonry is: 1/2 brick thick wall adopts staggered joints and 1/2 brick length masonry; 1 brick and above thick wall adopts one top and one straight or lock package masonry method . The top or bottom layer of bricks of 1 brick and 1 brick thick masonry shall be top or side masonry.

(4) When both sides of the furnace wall are working surfaces (except for walls with a thickness of 1 brick or less), both sides are to be laid at the same time.

(5) The water-cooled wall header and the pipe side and the sliding support of the pipe side passing through the masonry shall not be fixed, and the special-shaped brick at the pull hook of the water-cooled wall shall not jam the ear plate of the water-cooled wall.

(6) When the refractory bricks and red bricks are assembled, when the refractory bricks are built with 6 to 8 layers of brick height, every 1 to 1.5m along the horizontal direction, 115mm long stretched bricks must be extended to the outer wall of the red bricks. Tensioned bricks should be disconnected on the same layer, and the upper and lower layers should be staggered.

(7) Гадна ханыг улаан тоосгоноор барихдаа агааржуулалтын нүх гаргах ёстой бөгөөд нөөцлөгдсөн талбайн хуваарилалт жигд байна. Нэгийг нь ойролцоогоор 2м2 талбайд нөөцөлж, DN15~20 хар төмөр хоолойгоор булж болно (зайлшгүй тохиолдолд 60 × 120 мм нүхний аргыг ашиглана уу). Сараалжтай бойлерууд нь сараалжтай байх үед суурилуулж эхэлдэг; сараалжгүй бойлерыг ойролцоогоор 1м-ийн өндөрт байрлуулж эхлэх ба дулаалгын давхаргын хамгийн өндөр цэгийг мөн суурилуулж, зуухыг барьж дууссаны дараа шууд температурт тэсвэртэй материалаар зуухыг хаах ёстой.

6. The masonry of furnace wall openings, inspection holes, etc. adopts the masonry method that the refractory bricks of the inner wall penetrate to the red bricks of the outer wall (see Figure 2). When the upper covering design of the opening (hole) is required, the masonry shall be built according to the design requirements, and when the design is not required, the masonry shall be built in the following manner:

(1) The width of the hole (hole) in the wall is less than or equal to 450mm. If the span is not large, the solid platform method can be used to replace the small arch with a flat brick layer. The masonry method is shown in Figure 3. Each layer shall protrude ≤6mm from both sides into the opening until the opening is covered. The protruding length of each layer and the same layer shall be the same.

(2) Ханан дахь нүхний өргөн (нүх) ≤250мм нь тоосго боловсруулах замаар хучиж болно. Өрлөгийн аргыг Зураг 4-т үзүүлэв.

(3) The width of the hole in the wall> 450mm width shall be covered by arch-rotating masonry.

7. Masonry of arch and vault:

(1) The tire mold radius and radian production size required for arch and vault masonry must meet the design requirements. The span of the tire mold is less than the actual span by 20~30mm, the surface is flat and smooth, and it has load-bearing materials and construction loads without deformation Ability.

(2) Нуман өрлөгийн өмнө нуман хөлийн тоосгоны ард өрлөгийг дуусгах ёстой бөгөөд зөвхөн шалгалтыг давсны дараа өрлөгийг барьж болно. Нуман хөлийн тоосгоны дараа дулаан тусгаарлах галд тэсвэртэй тоосго, тоосгон замаг шороон тоосго барихыг хориглоно.

(3) Нуман оройг барихын өмнө нуман хаалга ба хүрээний багана нь хоорондоо ойрхон байх ёстой. Тохируулах хүрээний нуман хаалга тавихын өмнө хүрээ, зангилаа савааг тохируулж, засч, шалгалтыг давсан байх ёстой.

(4) Before the arch and vault masonry, first install the tire mold, check the elevation and position, fix it firmly, and then carry out pre-masonry. The purpose of pre-masonry is mainly to adjust the mortar joints and assemble the arch bricks. Model to meet the requirements of arch masonry quality and staggered joints. After the arch brick assembly arrangement meets the requirements, the brick faces are numbered according to the order of masonry and then removed, as shown in Figure 5. The masonry must be symmetrically built from the arch foot to the center at the same time. It is strictly forbidden to upside down the masonry.

(5) Unless there are special regulations, the arches and vaults shall be laid in staggered joints, and arches and vaults with different spans can be laid in rings. In the case of staggered joint masonry, when the length of the longitudinal joint is longer than 1 meter, the masonry must be drawn with a line.

(6) Lock bricks must be installed in the masonry of the arch and vault top. The depth of the built-in lock bricks is 2/3~3/4 of the thickness of the arch and vault top. As shown in Figure 6, the lock depth of the same arch must be the same. , When locking in, it should be from the tighter lock to the looser. In the wall, several adjacent arches and the lock bricks of the arch roof must be driven in at the same time to prevent the deformation of the adjacent arches.

(7) Цоожны тоосго нь жигд, тэгш хэмтэй тархсан. Нэг цоожтой тоосго руу <3м-ийн зайд, 3м-ээс>3м-ийн зайд XNUMX цоожтой тоосго өр. Түгжигдсэн үед та алх ашиглаж болно, гэхдээ энэ нь модон хавтангаар бүрхэгдсэн байх ёстой.

(8) Том гадаргууг шаантаг хэлбэртэй болгохын тулд 1/3-аас дээш зузаантай тоосго ашиглахыг хориглоно.

(9) For the processed bricks that are leveled on the upper part of the arch and the vault, the high temperature area or the surface of the external wall can be leveled by brick processing, and the low temperature area can be leveled by the same material of refractory concrete.

8. Дээшээ харсан өрлөг:

(1) Өрлөгийг эргүүлэхдээ дотор болон гадна талын хоёр нуман хэлбэртэй хавтанг хийдэг. Дотор нуман хавтан нь эргэлтийн радиусын дагуу хийгдсэн; гадна нуман хавтанг дотоод радиус дээр нэмээд эргэлдэх тоосгоны зузаантай хамт хийнэ.

(2) When building upside-down rotation, the bottom center line of the rotation is based on the arc-shaped slab, and the lower part is built. Generally, the length of the brick can meet 5~7 rotating bricks, then you can start to build upside down. Rotate, and then symmetrically build upside down from the center of the bottom of the upside down to both sides. Don’t hit too hard when starting to build to avoid shifting or loosening. After 5~7 bricks are built in the lower part of the inverted screw, the inner arc-shaped board is fixed on the surface of the rotating brick, and the bricks are symmetrically laid on both sides in the order of rotating the bricks and then processing the bricks. The masonry sequence is shown in Figure 7.

(3) 1/2 тойрог руу эргэх үед дээд 1/2 нь нуман хаалга, хонгилын өрлөгийг ашигладаг. Тоосго түгжихдээ дээд векторын өндрийн 1/2 орчимд тоосгоныг эргүүлж, дараа нь 8-р зурагт үзүүлсэн шиг өрлөгийн ажил дууссаны дараа тоосгоныг түгжих хэрэгтэй.

9. Өрлөгийн өрлөг, галын ханыг нураах:

(1) Hanging bricks and removing flame walls follow the principle of building from low to high, from the middle to both sides.

(2). Өргөх тоосго, дөл арилгагч хана барихад тоосго боловсруулах шаардлагатай бол дүүжлүүр тоосгоны дүүжлүүрийн нүхний зай 5 мм-ээс ихгүй, дөл арилгах хананы зузаан нь 90-ээс багагүй байна. %. Өргөгдсөн тоосгоны үндсэн хүч даах хэсгүүдэд ан цавгүй байх ёстой.

(3) For special-shaped bricks with fixing bolt holes, first dry row by layer for trial laying, and after marking the position of the bolt holes on the pipe, the fixing bolts can be welded. The nuts should not be tightened too tightly during masonry to avoid damaging the refractory bricks, and the bolt holes should be filled with refractory concrete.

10. Зуухны хананы өргөтгөлийн холбоосууд үлдсэн:

(1) Зуухны ханан дээрх өргөтгөлийн холболтын байршил, хэлбэр нь дизайны шаардлагад нийцсэн байна. Өргөнийг дизайны шаардлагаас бага байлгахыг хориглоно, эвдэрсэн тоосго гэх мэт хатуу эд зүйлсийг үе мөч рүү унахыг хориглоно. Өргөтгөх үе дэх савлагаа нь дизайны шаардлагын дагуу нягт савлагдсан байна. Шөрмөсөн олсыг ашиглахдаа дөлний гадаргуу дээр эхнийх нь галд тэсвэртэй шаварт дэвтээсэн байх ёстой.

(2) Water wall pipes, downcomers, headers, sewage pipes, drums, temperature measuring holes (tubes) and beams, etc., through the wall, leave expansion joints at the contact wall and the vertical and horizontal connections of the refractory brick furnace wall. It is better to wind with asbestos rope.

(3) The method of leaving the expansion joint of the furnace wall:

①. Булан дээр тэлэлтийн үеийг хадгалах аргыг Зураг 9(а)-д үзүүлэв: 1/2 тоосго, 1 тоосгоны уулзвараас гарах арга; Зураг 9(б): 1 тоосго, 1 тоосгоны уулзвараас гарах арга.

②. The method of setting expansion joints at the junction of the two ends of the demolition wall and the furnace wall is shown in Figure 10.

③. Зуухны хананы голд босоо тэлэлтийн үеийг байрлуулах аргыг Зураг 11-т үзүүлэв.

④. The method of setting expansion joints at the junction of the furnace roof and the two ends of the hanging arch and the furnace wall is shown in Figure 12.

⑤ The horizontal expansion joints of the furnace wall are generally made of special-shaped bricks. If there are no special-shaped bricks, the method shown in Figure 13 is used for masonry. When laying the horizontal expansion joint, the asbestos rope should be compressed; the height of the refractory bricks above the horizontal expansion joint should not exceed 1m, and the refractory bricks and red bricks will rise alternately to prevent the asbestos rope from being compressed and causing the furnace wall to tilt.

(4) The vertical expansion joint hangs the line for masonry, the wrong tooth is no more than 3mm, and the asbestos rope in the expansion joint is slightly larger than the remaining width of the expansion joint by 3~5mm, and it is pressed in at the same time during the masonry.

11. Refractory bricks and thermal insulation bricks are not allowed to wet the bricks, and the red bricks must be watered until the outside is dry and the inside is saturated before the red bricks are built.

12. It is not allowed to process bricks or walk on the masonry, and it is not allowed to face the processing surface of the bricks to the flame surface.

13. Галд тэсвэртэй тоосго, улаан тоосгоны гадаргууг холбох шаардлагатай. Конвекцийн хоолойн багцууд төвлөрч, бойлерийн дагалдах хэрэгсэл бөглөрсөн газруудад үнсний чихийг өрлөгийн хамт хусах шаардлагатай.

IMG_256

Construction is often a link that companies tend to ignore. They always think that good products and good designs can guarantee the service life of the kiln. In the national standard, there are strict regulations on the construction of rotary kiln, as follows: